It there any way to make the program "round" when entering calculations?

Steve EbnerUser is Offline
Member
Member
Send Private Message
Posts:374
Avatar

--
19 Aug 2008 11:37 PM  
"Do you mean to tell me that you aren't dealing with contractors who write estimates to replace 183.74 Sf Feet of paneling?" he asked facetiously.
Steve Ebner

"With great power comes great responsibility." (Stanley Lieber, Amazing Fantasy # 15 August 1962)
Ray HallUser is Offline
Veteran Member
Veteran Member
Send Private Message
Posts:897

--
19 Aug 2008 11:43 PM  

very good question... do and see what happens...

Roy CuppsUser is Offline
CatAdjuster.org
Member
Member
Send Private Message
Posts:359

--
20 Aug 2008 12:24 AM  

Yes,

Use RND() for example, RND(WC) will round to the nearest unit (square footage in this example) of the Wall and Ceiling area.  However, in most cases the actual area should be used unless you are dealing with something that involves waste and then the replacment of the item may be rounded up to the nearest full unit for example roofing but the removal should be based on the actual area. 

Adjuster Directory | The Licensing Page | The Cane Page
David DickersonUser is Offline
Member
Member
Send Private Message
Posts:34

--
20 Aug 2008 01:06 AM  


"Do you mean to tell me that you aren't dealing with contractors who write estimates to replace 183.74 Sf Feet of paneling?" he asked facetiously.

183.74 Sq ft of paneling = 6.44 sheets....  where do you buy .44 of a sheet he asked . 

 

Estimating is living on the edge between greed and fear
Bob HarveyUser is Offline
Member
Member
Send Private Message
Posts:440
Avatar

--
20 Aug 2008 01:49 AM  

Although I often note 32Sf, 64, 128, etc when dealing with smaller patches of drywall and paneling to allow for full sheets, we should keep in mind that the program is basing it's price on a 10% waste factor for paneling materials.

So if you are going room to room and scoping all the paneling to be replaced, I wouldn't want a reader to get the idea that everything needs to be rounded up to the nearest full sheet (like you do with bundles of roofing). Roofing and carpet don't have a waste factor built into the price because the software knows those items are often adjusted for waste by the estimator.  If you R&R carpet, Xm8 will suggest 15% waste on the "put back" but the other stuff like this paneling example isn't like that.  The material waste is built into the price. 

Here they are saying a 32 Sf sheet will "yield" 28.8 Sf

paneling waste

This is allowing 10% waste 32Sf - 3.2 = 28.8 Sf yield per sheet of paneling.

Posted By David Dickerson

183.74 Sq ft of paneling = 6.44 sheets....  where do you buy .44 of a sheet he asked . 

183.74 Sq ft divide by 32 = 5.74 sheets of actual surface area 
183.74 Sq ft divide by 28.8 "yield" = they are financially allowing for 6.38 sheets of materials to do this project. 

Who knows, maybe the contractor needs 7 full sheets. Added waste can be allowed when the project needs it, just keep in mind that Xm8 allows 10% and it's the same on hardwood flooring, 10%. 

If you are "burdoned" with using Xm8, you can click on the "i" next to the unit cost to get more information.  In this image you can see the paneling materials, how much adhesive and nails they are allowing, the labor rate of the installer, and the other tabs are going to show how they arrived at his productivity.

David DickersonUser is Offline
Member
Member
Send Private Message
Posts:34

--
20 Aug 2008 03:43 AM  
Bob
I was trying to get another debate going... just kidding...

I usually use the componant report in the summary tab, as I can highlight the rooms I am needing to see who much for example drywall is required. etc
Estimating is living on the edge between greed and fear
Bob HarveyUser is Offline
Member
Member
Send Private Message
Posts:440
Avatar

--
20 Aug 2008 04:20 AM  

Thats another good tool, you can see the combined material for all the rooms, or turn off selected rooms.

Today I did an estimate for a small cabin and it needed 100 Sf of T&G paneling in the ceiling, the materials allowed on that summary page shows 118 Sf, and the "info" on the unit price shows a yield of .85 so they have a 15% waste factor built into the material price.

118 Sf x .85 is rounded to the 100 Sf in my estimate, so that works out.

Component Materials

You are not authorized to post a reply.

Active Forums 4.1


Adjuster Chat Room Activity
Room:Users
The Den0



MyProfile

Introducing  "MyProfile", your space on CADO, create it, arrange it, share it! 
Click here to create your page!



An Adjuster to Adjuster Community

Privacy Statement  |  Terms Of Use
Copyright 1995-2007 by CatAdjuster.org Adjuster to Adjuster